Ditwah(CP)
Financial Dashboard
Financial Dashboard
2026-09-07
113,434,139.40
Contract Amount (LKR)
—
Advance Paid (LKR incl. VAT)
—
IPCs Paid (LKR incl. VAT)
— Mn
Financial Progress (0%)
113.4Mn
113.43 Mn
Total Contract
0.0Mn
— Mn
Advance Paid (incl. VAT)
0.0Mn
— Mn
IPCs Paid (incl. VAT)
0.0Mn
— Mn
Total Paid (incl. VAT)
23.8Mn
23.75 Mn
Advance Pend (VAT)
0.0Mn
— Mn
IPCs Pend (VAT)
Overall
0%
Financial Progress
Planned
40.6%
Planned Financial Progress
All
Hanguranketha
Kadugannawa
Kandy
Kundasale
Matale
Nalanda
Norwood
NuwaraEliya
Project-wise mode — 1 projects in one graph
Single Project
RDA/DRP/CEN/KDY/KUN/27
Kundasale
Kandy - Jaffna Road
Kandy Kundasale Team Leader
Financial Waterfall — RDA/DRP/CEN/KDY/KUN/27 (LKR Mn)
Advance + IPCs Paid + Pending + Remaining = Contract Amount
Financial Progress
0% actual0%Actual
— Mn
Total Paid
23.75 Mn
Pending
Planned vs Actual
40.6% planned40.6%
Planned
0%
Actual
-40.6% behind
Financial Summary
Advance payments, IPCs & expenditure per awarded project
1 projects
Export XLSX
113.4 Mn
Total Contract
0.0 Mn
Total Paid (incl. VAT)
23.8 Mn
Pending Payments
0% / planned 40.6%
Financial Progress (Paid / Contract)
| Contract No | Contract (LKR) |
Advance Paid (excl. VAT) |
Advance Paid (incl. VAT) |
Advance Pend (excl. VAT) |
Advance Pend (incl. VAT) |
IPCs Paid (excl. VAT) |
IPCs Paid (incl. VAT) |
IPCs Pend (excl. VAT) |
IPCs Pend (incl. VAT) |
Overall Expenditure (excl. VAT) |
Pending Payments (excl. VAT) |
Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| RDA/DRP/CEN/KDY/KUN/27 | 113,434,139.40 | — | — | 20,128,022.37 | 23,751,066.40 | — | — | — | — | — | 20,128,022.37 | — |
23.75Mn
20.9%
|