Ditwah(CP)
Financial Dashboard
Financial Dashboard
2026-09-07
188,617,394.68
Contract Amount (LKR)
—
Advance Paid (LKR incl. VAT)
—
IPCs Paid (LKR incl. VAT)
— Mn
Financial Progress (0%)
188.6Mn
188.62 Mn
Total Contract
0.0Mn
— Mn
Advance Paid (incl. VAT)
0.0Mn
— Mn
IPCs Paid (incl. VAT)
0.0Mn
— Mn
Total Paid (incl. VAT)
0.0Mn
— Mn
Advance Pend (VAT)
0.0Mn
— Mn
IPCs Pend (VAT)
Overall
0%
Financial Progress
Planned
24.1%
Planned Financial Progress
Single Project
RDA/DRP/CEN/NUE/NUR/98
Norwood
Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Harangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)
NuwaraEliya Norwood Norwood EE
Financial Waterfall — RDA/DRP/CEN/NUE/NUR/98 (LKR Mn)
Advance + IPCs Paid + Pending + Remaining = Contract Amount
Financial Progress
0% actual0%Actual
— Mn
Total Paid
— Mn
Pending
Planned vs Actual
24.1% planned24.1%
Planned
0%
Actual
-24.1% behind
Financial Summary
Advance payments, IPCs & expenditure per awarded project
1 projects
Export XLSX
188.6 Mn
Total Contract
0.0 Mn
Total Paid (incl. VAT)
0.0 Mn
Pending Payments
0% / planned 24.1%
Financial Progress (Paid / Contract)
| Contract No | Contract (LKR) |
Advance Paid (excl. VAT) |
Advance Paid (incl. VAT) |
Advance Pend (excl. VAT) |
Advance Pend (incl. VAT) |
IPCs Paid (excl. VAT) |
IPCs Paid (incl. VAT) |
IPCs Pend (excl. VAT) |
IPCs Pend (incl. VAT) |
Overall Expenditure (excl. VAT) |
Pending Payments (excl. VAT) |
Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| RDA/DRP/CEN/NUE/NUR/98 | 188,617,394.68 | — | — | — | — | — | — | — | — | — | — | — | — |