Ditwah(CP) Financial Dashboard

Financial Dashboard

2026-09-07

17,458,592.78

Contract Amount (LKR)

3,186,956.07

Advance Paid (LKR incl. VAT)

IPCs Paid (LKR incl. VAT)

3.19 Mn

Financial Progress (18.3%)

17.5Mn

17.46 Mn

Total Contract

3.2Mn

3.19 Mn

Advance Paid (incl. VAT)

0.0Mn

Mn

IPCs Paid (incl. VAT)

3.2Mn

3.19 Mn

Total Paid (incl. VAT)

0.0Mn

Mn

Advance Pend (VAT)

2.5Mn

2.46 Mn

IPCs Pend (VAT)

Overall

18.3%

Financial Progress

Planned

53.5%

Planned Financial Progress

Single Project RDA/DRP/CEN/MTL/NAL/51

Bowathenna Access Road (B-064) (0+000-2+410)

Matale Nalanda Nalanda EE

Financial Waterfall — RDA/DRP/CEN/MTL/NAL/51 (LKR Mn)

Advance + IPCs Paid + Pending + Remaining = Contract Amount

Financial Progress
18.3% actual
18.3%Actual

3.19 Mn

Total Paid

2.46 Mn

Pending

Planned vs Actual
53.5% planned

53.5%

Planned

18.3%

Actual

-35.2% behind
Financial Summary

Advance payments, IPCs & expenditure per awarded project

1 projects Export XLSX

17.5 Mn

Total Contract

3.2 Mn

Total Paid (incl. VAT)

2.5 Mn

Pending Payments

18.3% / planned 53.5%

Financial Progress (Paid / Contract)

Contract No Contract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial Progress Financial Progress
with Outstanding
RDA/DRP/CEN/MTL/NAL/51 17,458,592.78 2,700,844.13 3,186,956.07 2,081,765.34 2,456,483.12 2,700,844.13 2,081,765.34
3.19Mn
18.3%
Behind
5.64Mn
32.3%