RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE 36
MITIGATION OF FAILURE LOCATIONS ALONG PERADENIYA BADULLA CHENKALADI ROAD (A005) (38+200 & 41+800) AND SLOPE FAILURES DUE TO "DITWAH" CYCLONE -PACKAGE 36
Nuwara EliyaCentral ProvinceNuwara EliyaDivisional Secretariat-ContractorLKR —Contract Sum0 daysProject Duration
0%
Complete
Physical Progress0%
Planned Progress0%
Time Elapsed0%
On Track0days left
On Track • 0 days left
Project Timeline
LOA
–
PendingPossession
–
PendingCommencement
–
PendingScheduled Completion
–
PendingAnticipated Completion Date
–
PendingSwipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictNuwara Eliya
PD RegionCentral Province
CE RegionNuwara Eliya
EE DivisionNuwara Eliya
Package No.-
Tender By-
Scope
Contract NameMITIGATION OF FAILURE LOCATIONS ALONG PERADENIYA BADULLA CHENKALADI ROAD (A005) (38+200 & 41+800) AND SLOPE FAILURES DUE TO "DITWAH" CYCLONE -PACKAGE 36
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE 36
Tender Batch No.-
Contractor Name-
Consultant-
Tender StatusBid Evaluation and Tender Board Decision
LOA Date—
Contract Amount—
Engineer Estimate Amount (LKR)384,000,000.00
Duration (Days)-
CategoryDC - Slope
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
