DRRRP Awarded Slope

RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-03

MITIGATION OF SLOPE FAILURE LOCATIONS ALONG GOMBURU OYA-BALAPOKUNA ROAD (B582) 6+900 KM-7+100 KM DUE TO DITWAH CYCLONE - PACKAGE 03

Nuwara EliyaCentral ProvinceNuwara EliyaDivisional SecretariatNagma Engineering (Pvt) LtdContractorLKR 357,941,434.50Contract Sum273 daysProject Duration
0%
Complete
Physical Progress0%
Planned Progress0%
Time Elapsed0%
On Track • 0 days left

Project Timeline

LOA
2026-10-28
Completed
Possession
–
Pending
Commencement
–
Pending
Scheduled Completion
–
Pending
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictNuwara Eliya
PD RegionCentral Province
CE RegionNuwara Eliya
EE DivisionNuwara Eliya
Package No.-
Tender ByDC
Scope
Contract NameMITIGATION OF SLOPE FAILURE LOCATIONS ALONG GOMBURU OYA-BALAPOKUNA ROAD (B582) 6+900 KM-7+100 KM DUE TO DITWAH CYCLONE - PACKAGE 03
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-03
Tender Batch No.-
Contractor NameNagma Engineering (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-10-28
Contract Amount357,941,434.50
Engineer Estimate Amount (LKR)262,030,000.00
Duration (Days)273
CategoryDC - Slope