Project Monitoring Dashboard

Comprehensive overview of 3 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 12:46Live
Graphs reflect current view:3 awarded · Eastern Province · Ampara
0%

0

On Progress

0 / 3 awarded

33.3%

0

Delay

1 / 3 awarded

0%

0

Completed

0 / 3 awarded

Portfolio Breakdown · Eastern Province · Ampara · District

9Awarded12Total
Ampara 3 awarded of 5 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp ex-VATPlanned %Actual %
Emergency330100%464.0395.9367.220.55% of contract94.8%47.3%
DC - Roads2020%630.10.0————
DC - Slope0000%0.00.0————
PD(CP) - Slope0000%0.00.0————
Ampara53260%1,094.1395.9367.220.55% of contract94.8%47.3%

Avg Physical Progress per EE Division · Eastern Province · Ampara

Portfolio Timeline· 3 scheduled projects · Eastern Province · Ampara Toggle
Portfolio · Awarded Works

Awarded Projects

3 projects

3/3

Filter awarded works

3 matching projects

Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/EAS/AMP/AMP/01
Rehabilitation / Improvement of Ampara Uhana Mahoya Road (from 2+400 to 2+800) & (from 3+700 to 3+900), Siyambalanduwa Damana Ampara Road (from 43+000 to 45+000), (from 33+000 to 34+000), (from 35+500 to 36+500) & (from 52+000 to 53+000) and Chadayanthalawa Uhana Road (from 11+100 to 11+500)
90%
27,878,955.0231,793,559.86Awarded
RDA/DRP/EAS/AKK/AKK/04
Rehabilitation / Improvement of Newguna – Manikkamadu – Irakkamam Road (0+000-1+250) & (1+300-2+600), Akkaraipattu Degavapi Vangamam Road (8+500-21+500) and Reconstruction of Culvert No. 368/2 on Colombo-Ratnapura-Wellawaya-Batticaloa Road
29%
171,572,395.05196,038,211.02Awarded
RDA/DRP/EAS/AKK/KAL/05
Rehabilitation / Improvement and Reconstruction of Box Culvert at 9+780, Construction of Mass Concrete Retaining Wall (9+550 -9+600) & (9+600-11+000) on Sammanthurai - Malkampiddi - Deegawapi Road, Construction of Concrete Drain & rock blasting with utility shifting on Varaipathanchenai - Deegawapi Road (0+880 - 0+980 RHS), Construction of Concrete Drain on Deegawapi Temple Road (1+100 1+230 RHS), Construction of Mass Concete Retaining wall on Ampilanthurai - Veeramunai Road (25+600 - 26+000 LHS & RHS), Reconstruction of Wing Walls (at 375/2, 375/3, 375/4, 375/6) & Construction of Concrete Drain (384+000-389+000) on Colombo Ratnepura Wellawaya Batticoala Road, Construction of Concrete Drain (15+400 - 15+550 LHS) on Karaitivu - Ampara Road, Construction of Mass Concete Retaining Wall (5+700 -5+730) & on Construction of Hard Shoulder (Concrete) (13+200 - 13+600 LHS & RHS Selected Section) on Weeragoda - Central Camp Road, Construction of Hard Shoulder (Concete) (0+600 - 0+800 LHS & RHS) on Approach Road to Public Buildings
23%
196,448,155.48236,184,712.99Awarded
Showing 1–3 of 3
Per page:
Source: DRRRP • 5 projects • Data updated 2026-11-04 12:46 • 14:25:07