DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 6 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 16:23Live
Graphs reflect current view:6 awarded · Kurunegala
0%

0

On Progress

0 / 6 awarded

0%

0

Delay

0 / 6 awarded

0%

0

Completed

0 / 6 awarded

Portfolio Breakdown · Kurunegala · District

171Awarded266Total
Kurunegala 6 awarded of 6 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp ex-VATPlanned %Actual %
Emergency660100%640.7843.3562.255.07% of contract65.1%25.0%
DC - Roads0000%0.00.0————
DC - Slope0000%0.00.0————
PD(CP) - Slope0000%0.00.0————
Kurunegala660100%640.7843.3562.255.07% of contract65.1%25.0%

Avg Physical Progress per EE Division · Kurunegala

Portfolio Timeline· 6 scheduled projects · Kurunegala Toggle
Portfolio · Awarded Works

Awarded Projects

2 projects

2/2 (filtered)

Filter awarded works

2 matching projects2 active

ActiveDelayed onlyCritical Delay
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/NWP/KURU/KURU/04
Rehabilitation / Improvement of Muththettugala Hiripitiya Road (B300) (10+880 - 11+080) & Vilakatupotha Ganewatta Kumbukgete road (B478) (9+100 - 9+400)
62%
97,503,423.17105,193,927.73Awarded
RDA/DRP/NWP/KURU/MAHO/05
Rehabilitation / Improvement of Galgamuwa - Nikawewa Road (B126) (6+000-20+000), Danikithawa - Ambanpola Road (B089) (20+925 - 21+000), Nikaweratiya - Moragollagama - Siyambalangamuwa Road (B326) (40+760 - 48+240), Malsiripura - Rambe Road (B610) (7+500 - 9+650), Ibbagamuwa - Kumbukgate - Madagalla Road (B159) (16+450 - 28+680), Hiripitiya - Galtenwewa Road (B609) (9+580-9+680), Padeniya - Anuradapura Road (AA028) (8+480-8+800) and Katugasthota - Kurunegala - Puththalama Road (AA010) (73+745-73 -870) in Maho EE Division
70%
151,515,024.36166,163,663.09Awarded
Showing 1–2 of 2
Per page:
Source: DRRRP • 6 projects • Data updated 2026-11-04 16:23 • 16:36:21