DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 6 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-04 16:23Live
Graphs reflect current view:6 awarded · Anuradhapura
100% awarded
0
Awarded
6 total projects in portfolio
Awarded projects6
RDA/DPR/NCP/ANU/ANU/02RDA/DPR/NCP/ANU/ANU/03RDA/DPR/NCP/ANU/ANU/01RDA/DRP/NCP/ANU/MAR/05RRDA/DRP/NCP/ANU/MAR/06RDA/DRP/NCP/ANU/MED/07
Click to filter the awarded table
610.8M
610.8 Mn
Contract Value
Awarded projects6
RDA/DPR/NCP/ANU/ANU/02RDA/DPR/NCP/ANU/ANU/03RDA/DPR/NCP/ANU/ANU/01RDA/DRP/NCP/ANU/MAR/05RRDA/DRP/NCP/ANU/MAR/06RDA/DRP/NCP/ANU/MED/07
Click to filter the awarded table
Avg
42.2%
6
works in progress
0 completed
Avg Progress
Awarded projects6
RDA/DPR/NCP/ANU/ANU/02RDA/DPR/NCP/ANU/ANU/03RDA/DPR/NCP/ANU/ANU/01RDA/DRP/NCP/ANU/MAR/05RRDA/DRP/NCP/ANU/MAR/06RDA/DRP/NCP/ANU/MED/07
Click to filter the awarded table
93.5M
93.5 Mn
Total Expenditure (incl. VAT)
Awarded projects6
RDA/DPR/NCP/ANU/ANU/02RDA/DPR/NCP/ANU/ANU/03RDA/DPR/NCP/ANU/ANU/01RDA/DRP/NCP/ANU/MAR/05RRDA/DRP/NCP/ANU/MAR/06RDA/DRP/NCP/ANU/MED/07
Click to filter the awarded table
0%
0
On Progress
0 / 6 awarded
On Progress (incl. completed)0
No projects
Click to filter the awarded table
83.3%
0
Critical Delay
5 / 6 awarded
Critical Delay5
RDA/DPR/NCP/ANU/ANU/02RDA/DPR/NCP/ANU/ANU/03RDA/DPR/NCP/ANU/ANU/01RDA/DRP/NCP/ANU/MAR/05RRDA/DRP/NCP/ANU/MED/07
Click to filter the awarded table
0%
0
Completed
0 / 6 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Anuradhapura · District
Avg Physical Progress per EE Division · Anuradhapura
At-Risk Projects · Anuradhapura
- RDA/DRP/NCP/ANU/MED/07Rehabilitation / Improvement of Flood Damaged - Shoulder & Embankment Protection for Puttalam - Trincomalee Road (AA012) (131+100-131+400 LHS/RHS) (139+020-139+100 LHS) , Kandy -Jaffna Road (AA009) ( 148+775-149+050) and Kebithigollewa - Padaviya Road (B211) (17+400-17+550)Delay299 Days in Delay · 47%
- RDA/DRP/NCP/ANU/MAR/06Rehabilitation / Improvement and Retaining wall Construction of bridge No. 3/1 & Gabion wall Construction on Madatugama Pubbogama Andiyagala Road (B-556) (1+900km) RHSDelay36 Days in Delay · 90%
- RDA/DPR/NCP/ANU/ANU/02Rehabilitation / Improvement and Construction of Drainge Canal for Kumbichchan Kulama Spillway on Maitreepala Senanayake Mawatha (1+970 - 2+090 km)Delay16 Days in Delay · 50%
- RDA/DPR/NCP/ANU/ANU/03Rehabilitation / Improvement Construction of Drainge Canal for Thambuttegama Tank Spill on Padeniya - Anuradhapura Road (59+420 - 59+610) & Construction of Drainge Canal for Protection Road on Andarawewa - Balaluwewa Road(16+580 - 16+680)Delay16 Days in Delay · 38%
- RDA/DPR/NCP/ANU/ANU/01Rehabilitation / Improvement of Andarawewa - Balaluwewa Road (B501) (21+330 - 21+ 580 km)Delay13 Days in Delay · 16%
Portfolio Timeline· 6 scheduled projects · Anuradhapura Toggle
2026-02-06 today2026-11-27
Portfolio · Awarded Works
Awarded Projects
5 projects
Filter awarded works
5 matching projects1 active
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DPR/NCP/ANU/ANU/02 | Rehabilitation / Improvement and Construction of Drainge Canal for Kumbichchan Kulama Spillway on Maitreepala Senanayake Mawatha (1+970 - 2+090 km) | 50% | 138,891,057.65 | 178,990,814.77 | Awarded |
| RDA/DPR/NCP/ANU/ANU/03 | Rehabilitation / Improvement Construction of Drainge Canal for Thambuttegama Tank Spill on Padeniya - Anuradhapura Road (59+420 - 59+610) & Construction of Drainge Canal for Protection Road on Andarawewa - Balaluwewa Road(16+580 - 16+680) | 38% | 132,437,825.50 | 174,596,369.90 | Awarded |
| RDA/DPR/NCP/ANU/ANU/01 | Rehabilitation / Improvement of Andarawewa - Balaluwewa Road (B501) (21+330 - 21+ 580 km) | 16% | 99,497,834.48 | 85,106,787.10 | Awarded |
| RDA/DRP/NCP/ANU/MAR/06 | Rehabilitation / Improvement and Retaining wall Construction of bridge No. 3/1 & Gabion wall Construction on Madatugama Pubbogama Andiyagala Road (B-556) (1+900km) RHS | 90% | 112,693,093.11 | 91,709,767.42 | Awarded |
| RDA/DRP/NCP/ANU/MED/07 | Rehabilitation / Improvement of Flood Damaged - Shoulder & Embankment Protection for Puttalam - Trincomalee Road (AA012) (131+100-131+400 LHS/RHS) (139+020-139+100 LHS) , Kandy -Jaffna Road (AA009) ( 148+775-149+050) and Kebithigollewa - Padaviya Road (B211) (17+400-17+550) | 47% | 38,223,285.38 | 45,054,035.76 | Awarded |
Showing 1–5 of 5
Source: DRRRP • 6 projects • Data updated 2026-11-04 16:23 • 16:29:53 System live • Sri Lanka • 1 districts