DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 6 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-04 12:46Live
Graphs reflect current view:6 awarded · Kurunegala
100% awarded
0
Awarded
6 total projects in portfolio
Awarded projects6
RDA/DRP/NWP/KURU/KULI/01RRDA/DRP/NWP/KURU/KURU/02RRDA/DRP/NWP/KURU/KURU/03RRDA/DRP/NWP/KURU/KURU/04RDA/DRP/NWP/KURU/MAHO/05RDA/DRP/NWP/KURU/MAHO/06R
Click to filter the awarded table
843.3M
843.3 Mn
Contract Value
Awarded projects6
RDA/DRP/NWP/KURU/KULI/01RRDA/DRP/NWP/KURU/KURU/02RRDA/DRP/NWP/KURU/KURU/03RRDA/DRP/NWP/KURU/KURU/04RDA/DRP/NWP/KURU/MAHO/05RDA/DRP/NWP/KURU/MAHO/06R
Click to filter the awarded table
Avg
25%
4
works in progress
0 completed
Avg Progress
Awarded projects6
RDA/DRP/NWP/KURU/KULI/01RRDA/DRP/NWP/KURU/KURU/02RRDA/DRP/NWP/KURU/KURU/03RRDA/DRP/NWP/KURU/KURU/04RDA/DRP/NWP/KURU/MAHO/05RDA/DRP/NWP/KURU/MAHO/06R
Click to filter the awarded table
64.8M
64.8 Mn
Total Expenditure (incl. VAT)
Awarded projects6
RDA/DRP/NWP/KURU/KULI/01RRDA/DRP/NWP/KURU/KURU/02RRDA/DRP/NWP/KURU/KURU/03RRDA/DRP/NWP/KURU/KURU/04RDA/DRP/NWP/KURU/MAHO/05RDA/DRP/NWP/KURU/MAHO/06R
Click to filter the awarded table
0%
0
On Progress
0 / 6 awarded
On Progress (incl. completed)0
No projects
Click to filter the awarded table
0%
0
Delay
0 / 6 awarded
Delay0
No projects
Click to filter the awarded table
100%
0
Critical Delay
6 / 6 awarded
Critical Delay6
RDA/DRP/NWP/KURU/KULI/01RRDA/DRP/NWP/KURU/KURU/02RRDA/DRP/NWP/KURU/KURU/03RRDA/DRP/NWP/KURU/KURU/04RDA/DRP/NWP/KURU/MAHO/05RDA/DRP/NWP/KURU/MAHO/06R
Click to filter the awarded table
0%
0
Completed
0 / 6 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Kurunegala · District
Avg Physical Progress per EE Division · Kurunegala
At-Risk Projects · Kurunegala
- RDA/DRP/NWP/KURU/KURU/04Rehabilitation / Improvement of Muththettugala Hiripitiya Road (B300) (10+880 - 11+080) & Vilakatupotha Ganewatta Kumbukgete road (B478) (9+100 - 9+400)Delay105 Days in Delay · 62%
- RDA/DRP/NWP/KURU/MAHO/05Rehabilitation / Improvement of Galgamuwa - Nikawewa Road (B126) (6+000-20+000), Danikithawa - Ambanpola Road (B089) (20+925 - 21+000), Nikaweratiya - Moragollagama - Siyambalangamuwa Road (B326) (40+760 - 48+240), Malsiripura - Rambe Road (B610) (7+500 - 9+650), Ibbagamuwa - Kumbukgate - Madagalla Road (B159) (16+450 - 28+680), Hiripitiya - Galtenwewa Road (B609) (9+580-9+680), Padeniya - Anuradapura Road (AA028) (8+480-8+800) and Katugasthota - Kurunegala - Puththalama Road (AA010) (73+745-73 -870) in Maho EE DivisionDelay64 Days in Delay · 70%
Portfolio Timeline· 6 scheduled projects · Kurunegala Toggle
2026-04-21 today2027-03-29
Portfolio · Awarded Works
Awarded Projects
2 projects
Filter awarded works
2 matching projects1 active
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DRP/NWP/KURU/KURU/04 | Rehabilitation / Improvement of Muththettugala Hiripitiya Road (B300) (10+880 - 11+080) & Vilakatupotha Ganewatta Kumbukgete road (B478) (9+100 - 9+400) | 62% | 97,503,423.17 | 105,193,927.73 | Awarded |
| RDA/DRP/NWP/KURU/MAHO/05 | Rehabilitation / Improvement of Galgamuwa - Nikawewa Road (B126) (6+000-20+000), Danikithawa - Ambanpola Road (B089) (20+925 - 21+000), Nikaweratiya - Moragollagama - Siyambalangamuwa Road (B326) (40+760 - 48+240), Malsiripura - Rambe Road (B610) (7+500 - 9+650), Ibbagamuwa - Kumbukgate - Madagalla Road (B159) (16+450 - 28+680), Hiripitiya - Galtenwewa Road (B609) (9+580-9+680), Padeniya - Anuradapura Road (AA028) (8+480-8+800) and Katugasthota - Kurunegala - Puththalama Road (AA010) (73+745-73 -870) in Maho EE Division | 70% | 151,515,024.36 | 166,163,663.09 | Awarded |
Showing 1–2 of 2
Source: DRRRP • 6 projects • Data updated 2026-11-04 12:46 • 14:34:55 System live • Sri Lanka • 1 districts