DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 3 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-04 16:23Live
Graphs reflect current view:3 awarded · Ampara
60% awarded
0
Awarded
5 total projects in portfolio
Awarded projects3
Click to filter the awarded table
395.9M
395.9 Mn
Contract Value
Awarded projects3
Click to filter the awarded table
Avg
47.3%
3
works in progress
0 completed
Avg Progress
Awarded projects3
Click to filter the awarded table
24.2M
24.2 Mn
Total Expenditure (incl. VAT)
Awarded projects3
Click to filter the awarded table
0%
0
On Progress
0 / 3 awarded
On Progress (incl. completed)0
No projects
Click to filter the awarded table
0%
0
Completed
0 / 3 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Ampara · District
Avg Physical Progress per EE Division · Ampara
Portfolio Timeline· 3 scheduled projects · Ampara Toggle
2026-06-12 today2026-12-10
Portfolio · Awarded Works
Awarded Projects
1 projects
Filter awarded works
1 matching project1 active
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DRP/EAS/AMP/AMP/01 | Rehabilitation / Improvement of Ampara Uhana Mahoya Road (from 2+400 to 2+800) & (from 3+700 to 3+900), Siyambalanduwa Damana Ampara Road (from 43+000 to 45+000), (from 33+000 to 34+000), (from 35+500 to 36+500) & (from 52+000 to 53+000) and Chadayanthalawa Uhana Road (from 11+100 to 11+500) | 90% | 27,878,955.02 | 31,793,559.86 | Awarded |
Showing 1–1 of 1
Source: DRRRP • 5 projects • Data updated 2026-11-04 16:23 • 17:22:36 System live • Sri Lanka • 1 districts