DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 1 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka. · Team Leader

Updated 2026-11-04 12:46Live
Graphs reflect current view:1 awarded · Team Leader · EE: Kadugannawa
0%

0

On Progress

0 / 1 awarded

0%

0

Delay

0 / 1 awarded

0%

0

Completed

0 / 1 awarded

Portfolio Breakdown · Team Leader · EE: Kadugannawa · EE Office

26Awarded26Total
Kadugannawa 1 awarded of 1 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Emergency110100%275.5193.4193.458.230% of contract100.0%26.5%
DC - Roads0000%0.00.0————
DC - Slope0000%0.00.0————
PD(CP) - Slope0000%0.00.0————
Kadugannawa110100%275.5193.4193.458.230% of contract100.0%26.5%

Project-wise Progress · Team Leader · EE: Kadugannawa (1 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Team Leader · EE: Kadugannawa

Average Physical Progress by EE Division · Team Leader · EE: Kadugannawa

Average District-wise Physical Progress (Kandy District)

Kandy district baseline — all categories · EE: Kadugannawa (consultant filter excluded for comparison)

Portfolio Timeline· 1 scheduled projects · Team Leader · EE: Kadugannawa Toggle
2026-03-25 today2026-11-04
Portfolio · Awarded Works

Awarded Projects

1 projects

1/1 (filtered)

Filter awarded works

1 matching project1 active

ActiveDelayed only
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/KDY/KAD/11
Rehabilitation / Improvement of Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )
26.5%
193,404,194.96275,515,701.42Awarded
Showing 1–1 of 1
Per page:
Source: DRRRP • 1 projects • Data updated 2026-11-04 12:46 • 14:37:34