
Financial Dashboard
Monitor financial performance across 0 awarded projects
— Mn
Total Contract
— Mn
Advance Paid (excl. VAT)
— Mn
IPCs Paid (excl. VAT)
— Mn
Total Paid (excl. VAT)
— Mn
Total Paid (incl. VAT)
— Mn
Advance Pend (incl. VAT)
— Mn
IPCs Pend (incl. VAT)
— Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
0%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
0%
Planned Financial Progress
Planned share of contract value
Portfolio Breakdown — Financial (Exclusive Vat) · Northern Province · EE: Nuwara Eliya · EE Office
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| DC - Roads | 6 | 4,137.5 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 2 | 734.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Provinces | 14 | 6,123.4 | 304.65% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 36.1% | 4.2% |
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| DC - Roads | 6 | 4,137.5 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 2 | 734.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Central Province | 14 | 6,123.4 | 304.65% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 36.1% | 4.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| DC - Roads | 6 | 4,137.5 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 2 | 734.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Districts | 14 | 6,123.4 | 304.65% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 36.1% | 4.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| DC - Roads | 6 | 4,137.5 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 2 | 734.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya | 14 | 6,123.4 | 304.65% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 36.1% | 4.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| DC - Roads | 6 | 4,137.5 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 1 | 376.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Consultants | 13 | 5,765.5 | 304.65% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 38.9% | 4.5% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 498.2 | 51.410% of contract | 9.9 | 1 | 1 | 29.0 | 2 | 1 | 14.6 | 52.8% | 8.7% |
| DC - Roads | 6 | 4,137.5 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 1 | 376.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Team Leader | 9 | 5,012.3 | 51.41% of contract | 9.9 | 1 | 1 | 29.0 | 2 | 1 | 14.6 | 11.7% | 0.9% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 4 | 753.2 | 253.234% of contract | 9.7 | 3 | 3 | 128.7 | 9 | 3 | 85.9 | 100.0% | 28.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya EE | 4 | 753.2 | 253.234% of contract | 9.7 | 3 | 3 | 128.7 | 9 | 3 | 85.9 | 100.0% | 28.5% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 129 | 22,610.7 | 4,184.219% of contract | 207.2 | 81 | 78 | 2,556.7 | 122 | 60 | 989.5 | 85.7% | 15.7% |
| DC - Roads | 8 | 5,116.6 | 57.81% of contract | — | 1 | 1 | 49.0 | — | — | — | 0.5% | 1.0% |
| DC - Slope | 10 | 3,258.5 | — | — | — | — | — | — | — | — | 0.3% | 0.0% |
| PD(CP) - Slope | 8 | 177.7 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| All EE Offices | 155 | 31,163.5 | 4,242.014% of contract | 207.2 | 82 | 79 | 2,605.7 | 122 | 60 | 989.5 | 71.4% | 11.5% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| DC - Roads | 6 | 4,137.5 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 2 | 734.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya | 14 | 6,123.4 | 304.65% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 36.1% | 4.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 22 | 4,976.9 | 892.818% of contract | — | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Ratnapura | 22 | 4,976.9 | 892.818% of contract | 0.0 | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 19 | 4,275.2 | 951.322% of contract | — | 15 | 15 | 615.2 | 19 | 13 | 190.9 | 92.4% | 18.9% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Badulla | 19 | 4,275.2 | 951.322% of contract | 0.0 | 15 | 15 | 615.2 | 19 | 13 | 190.9 | 92.4% | 18.9% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 10 | 2,440.9 | 548.422% of contract | — | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kegalle | 10 | 2,440.9 | 548.422% of contract | 0.0 | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 369.1 | 34.09% of contract | — | 2 | 2 | 28.9 | — | — | — | 96.0% | 7.8% |
| DC - Roads | 2 | 979.2 | 57.86% of contract | — | 1 | 1 | 49.0 | — | — | — | 1.8% | 5.0% |
| DC - Slope | 2 | 484.8 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Norwood | 7 | 1,833.0 | 91.85% of contract | 0.0 | 3 | 3 | 77.8 | 0 | 0 | 0.0 | 41.7% | 4.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,105.1 | 271.425% of contract | 33.9 | 5 | 5 | 151.1 | 9 | 4 | 79.0 | 73.7% | 20.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 628.9 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 3 | 57.8 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Kundasale | 12 | 1,791.8 | 271.415% of contract | 33.9 | 5 | 5 | 151.1 | 9 | 4 | 79.0 | 49.1% | 12.8% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,345.4 | 272.220% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.2% | 17.1% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 372.1 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Matale | 7 | 1,717.6 | 272.216% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 65.3% | 13.4% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,447.4 | 253.117% of contract | — | 6 | 6 | 214.5 | — | — | — | 100.0% | 14.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Gampaha | 8 | 1,447.4 | 253.117% of contract | 0.0 | 6 | 6 | 214.5 | 0 | 0 | 0.0 | 100.0% | 14.8% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,433.0 | 196.214% of contract | — | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Colombo | 8 | 1,433.0 | 196.214% of contract | 0.0 | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Chilaw | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 768.2 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 72.5% | 7.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kurunegala | 5 | 768.2 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 72.5% | 7.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 610.8 | 93.515% of contract | — | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Anuradhapura | 6 | 610.8 | 93.515% of contract | 0.0 | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 47.8 | 9.219% of contract | — | 1 | 1 | 7.8 | — | — | — | 100.0% | 16.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 2 | 512.3 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Hanguranketha | 3 | 560.1 | 9.22% of contract | 0.0 | 1 | 1 | 7.8 | 0 | 0 | 0.0 | 33.3% | 1.4% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 386.7 | — | — | — | — | — | — | — | — | 2.7% | 0.0% |
| PD(CP) - Slope | 4 | 93.8 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Gampola | 5 | 480.5 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 0.5% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Jaffna | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 193.4 | 58.230% of contract | — | 1 | 1 | 33.3 | 4 | 1 | 16.0 | 100.0% | 25.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 139.1 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 1 | 26.1 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Kadugannawa | 3 | 358.6 | 58.216% of contract | 0.0 | 1 | 1 | 33.3 | 4 | 1 | 16.0 | 33.3% | 13.7% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 235.4 | 64.727% of contract | — | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Polonnaruwa | 5 | 235.4 | 64.727% of contract | 0.0 | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 221.8 | — | — | — | — | — | — | — | — | 19.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kandy | 3 | 221.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 19.2% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 160.3 | 59.237% of contract | — | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Monaragala | 2 | 160.3 | 59.237% of contract | 0.0 | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nalanda | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 49.2 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Trincomalee | 1 | 49.2 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 0.0% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 42.8 | — | — | — | — | — | — | — | — | 62.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Vavuniya | 1 | 42.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 62.5% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 37.3 | — | — | — | — | — | — | — | — | 81.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Mullaitivu | 1 | 37.3 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 81.5% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 28.4 | — | — | — | — | — | — | — | — | 100.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Galle | 2 | 28.4 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 100.0% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
Avg Physical Progress per Province · Northern Province · EE: Nuwara Eliya
No province data available
Awarded projects will appear here
Financial Progress per Province (Mn) Excluding VAT · Northern Province · EE: Nuwara Eliya
No province financial data available
Awarded projects will appear here
Avg Physical Progress per EE Division · Northern Province · EE: Nuwara Eliya
No data available
Awarded projects will appear here
Financial Progress per EE Division (Mn) Excluding VAT · Northern Province · EE: Nuwara Eliya
No financial data available
Awarded projects will appear here
District-wise Physical Progress · Northern Province · EE: Nuwara Eliya
No district data available
Awarded projects will appear here
District-wise Financial Progress (Mn) Excluding VAT · Northern Province · EE: Nuwara Eliya
No financial data available
Awarded projects will appear here
Consultant-wise Physical Progress · Northern Province · EE: Nuwara Eliya
No consultant data available
Awarded projects will appear here
Consultant-wise Financial Progress (Mn) Excluding VAT · Northern Province · EE: Nuwara Eliya
No financial data available
Awarded projects will appear here
Project-wise Physical Progress: Actual vs Planned (%) · Northern Province · EE: Nuwara Eliya (0)
No data available
Awarded projects will appear here
Project-wise Financial Progress: Actual vs Planned (Mn) Excluding VAT · Northern Province · EE: Nuwara Eliya (0)
No financial data available
Awarded projects will appear here
Project-wise Financials · Northern Province · EE: Nuwara Eliya (171 Projects)
Project-wise Contract Value vs. Expenditure and Pending Payments · Northern Province · EE: Nuwara Eliya (Mn · incl. VAT)
Scroll horizontally — 171 projects
Nuwara Eliya Division · Northern Province · EE: Nuwara Eliya (Mn · incl. VAT)
District District Summary (Mn · incl. VAT)
District baseline — overall all categories (consultant filter excluded for comparison) · amounts incl. VAT
Financial Summary
Advance payments, IPCs & expenditure per awarded project · 171 projects
Filter financial register
171 matching projects
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 41 | RDA/DC/DRP/SLOPE/PD(CP)/KDY/… | Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenk… | Weebadda Construction | 22,481,370.00 | — | — | — | — | — | — | — | — | — | — | — | — |
| 42 | RDA/DC/DRP/SLOPE/PD(CP)/KDY/… | Construction of Slope failure mitigation measures along Galaha-Pupuressa-Delpiti… | J. Kodithuwakkuarachchi & Sons (Pvt) Ltd | 17,724,816.00 | — | — | — | — | — | — | — | — | — | — | — | — |
| 43 | RDA/DC/DRP/SLOPE/PD(CP)/KDY/… | Construction of Slope failure mitigation measures along Atabage-Ulapane Road (B … | Bandaranayake Builders and Construction | 24,796,315.46 | — | — | — | — | — | — | — | — | — | — | — | — |
| 44 | RDA/DC/DRP/SLOPE/PD(CP)/KDY/… | Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenk… | Weebadda Construction | 28,806,688.50 | — | — | — | — | — | — | — | — | — | — | — | — |
| 45 | RDA/DC/DRP/SLOPE/PD(CP)/KDY/… | Construction of Slope failure mitigation measures along Kandy-Mahiyangana-Padiya… | J. Kodithuwakkuarachchi & Sons (Pvt) Ltd | 25,255,788.00 | — | — | — | — | — | — | — | — | — | — | — | — |
| 46 | RDA/DC/DRP/SLOPE/PD(CP)/KDY/… | Construction of Slope failure mitigation measures along Kandy – Mahiyangana – Pa… | J. Kodithuwakkuarachchi & Sons (Pvt) Ltd | 19,636,680.00 | — | — | — | — | — | — | — | — | — | — | — | — |
| 47 | RDA/DC/DRP/SLOPE/PD(CP)/KDY/… | Construction of Slope failure mitigation measures along KandyMahiyanganaPadiyath… | J. Kodithuwakkuarachchi & Sons (Pvt) Ltd | 12,938,500.00 | — | — | — | — | — | — | — | — | — | — | — | — |
| 48 | RDA/DC/DRP/SLOPE/PD(CP)/KDY/… | Construction of Slope failure mitigation measures along Aladeniya-Eriyagama Road… | Weebadda Construction | 26,072,370.00 | — | — | — | — | — | — | — | — | — | — | — | — |
| 49 | RDA/DRP/SAB/KEG/KEG/14 | Rehabilitation / Improvement of Damaged Locations in Colombo Kandy Road from 56+… | Tudawe Brothers (Pvt) Ltd | 261,228,130.78 | 47,252,023.78 | 55,757,388.06 | — | — | 20,746,920.91 | 24,481,366.67 | — | — | 67,998,944.69 | — | 80.24Mn Watch30.7% | 80.24Mn 30.7% |
| 50 | RDA/DRP/UVA/BAD/BAD/02 | Rehabilitation / Improvement of Demodara SpringValley Badulla Road (16+145-20+80… | Priyankara Industries & Contractors | 241,775,532.44 | — | — | — | — | 30,108,187.00 | 35,527,660.65 | — | — | 30,108,187.00 | — | 35.53Mn Behind14.7% | 35.53Mn 14.7% |
| Total | 34,005,299,486.17 | 2,787,819,645.29 | 3,289,427,166.63 | 113,218,826.01 | 133,598,214.69 | 1,049,943,508.60 | 1,238,847,524.51 | 63,842,351.18 | 73,647,937.02 | 3,837,763,153.89 | 177,061,177.19 | 4,528.27Mn 13.3% | 4,735.52Mn 13.9% | |||