DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 5 awarded projects

2026-11-04
21:48:35Live2026-11-04
0 / 5Advance Pendingpending advance projects / total projects
0 / 5IPC Pendingpending IPC projects / total projects
3 / 5Advance Paidadvance paid projects / total projects
3 / 5IPCs PaidIPC paid projects / total projects
235.4 Mn

235.36 Mn

Total Contract

28.1 Mn

28.13 Mn

Advance Paid (excl. VAT)

26.7 Mn

26.67 Mn

IPCs Paid (excl. VAT)

54.8 Mn

54.81 Mn

Total Paid (excl. VAT)

64.7 Mn

64.67 Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

64.7 Mn

64.67 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

23.3%

23.3%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

100%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Polonnaruwa · District

171Projects34,005.3Contract Mn
Reset
Polonnaruwa 5 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency5235.464.727% of contract—3328.13326.7100.0%23.3%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Polonnaruwa5235.464.727% of contract0.03328.13326.7100.0%23.3%
Emergency5 projects235.4Mn
27% paid64.7 Mn
Pending—
Planned Fin100.0%
Actual Fin23.3%
Advance & IPC
Advance paid3 proj · 28.1 Mn
IPC paid3 proj · 26.7 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Polonnaruwa5 projects235.4Mn
27% paid64.7 Mn
Pending0.0Mn
Planned Fin100.0%
Actual Fin23.3%

Avg Physical Progress per Province · Polonnaruwa

Graphs reflect current view:5 awarded · Polonnaruwa
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 171 projects

141–150/171

Filter financial register

171 matching projects

S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
141RDA/DRP/NCP/POL/POL/08
Rehabilitation / Improvement and Reconstruction of 31/1 Culvert, Construction Of…
Sawsiri Construction
17,459,311.37————9,866,233.2111,642,155.19——9,866,233.21—
11.64Mn
66.7%
On Track
11.64Mn
66.7%
142RDA/DRP/NCP/POL/POL/10
Rehabilitation / Improvement and Construction of New Drainage At 65-78km on Mara…
A.D.M Construction
29,767,050.534,266,131.965,034,035.72——6,804,713.268,029,561.65——11,070,845.22—
13.06Mn
43.9%
On Track
13.06Mn
43.9%
143RDA/DRP/UVA/BAD/BAN/24
Rehabilitation / Improvement of Rendapola Ambewela Road
Gamage Builders
290,409,872.9652,259,795.0761,666,558.18——————52,259,795.07—
61.67Mn
21.2%
Watch
61.67Mn
21.2%
144RDA/DRP/EAS/AMP/AMP/01
Rehabilitation / Improvement of Ampara Uhana Mahoya Road (from 2+400 to 2+800) &…
Ediriweera Construction
27,878,955.025,042,900.915,950,623.07——————5,042,900.91—
5.95Mn
21.3%
Watch
5.95Mn
21.3%
145RDA/DRP/EAS/AKK/AKK/04
Rehabilitation / Improvement of Newguna – Manikkamadu – Irakkamam Road (0+000-1+…
Jeezan Trading and Transport
171,572,395.0515,455,490.4618,237,478.74——————15,455,490.46—
18.24Mn
10.6%
Behind
18.24Mn
10.6%
146RDA/DRP/EAS/AKK/KAL/05
Rehabilitation / Improvement and Reconstruction of Box Culvert at 9+780, Constru…
Nazeeha Hardware and Construction
196,448,155.48————————————
147RDA/DRP/NWP/CHI/PUT/12
Rehabilitation / Improvement of Puttalam Marichchikaddi Road in Puttalam 6+100-9…
Omega Construction Company (Pvt) Ltd
141,404,654.67——25,503,937.2130,094,645.91—————25,503,937.21—
30.09Mn
21.3%
148RDA/DRP/WP/GAM/GAM/13
Rehabilitation / Improvement and Culvert Constructions on Aluthgama- Vigoda Road…
Venus Enterprise
34,489,854.85————————————
149RDA/DRP/NCP/POL/POL/11
Rehabilitation / Improvement and Construction of New Drainage on Polonnaruwa-Tha…
A.D.M Construction
44,474,738.827,582,108.448,946,887.96——————7,582,108.44—
8.95Mn
20.1%
Watch
8.95Mn
20.1%
150RDA/DRP/SAB/RAT/PEL/18
Rehabilitation / Improvement of Oluganthota - Pinnawala - Bagawanthalawa (26+000…
Anura Construction
169,799,736.07————————————
Total34,005,299,486.172,787,819,645.293,289,427,166.63113,218,826.01133,598,214.691,049,943,508.601,238,847,524.5163,842,351.1873,647,937.023,837,763,153.89177,061,177.19
4,528.27Mn
13.3%
4,735.52Mn
13.9%
Showing 141–150 of 171 projects · page 15/18