Pending—
Planned Fin100.0%
Actual Fin14.8%
Advance & IPC
Advance paid6 proj · 214.5 Mn
IPC paid0 proj · 0.0 Mn
Monitor financial performance across 9 awarded projects
2,114.04 Mn
Total Contract
214.46 Mn
Advance Paid (excl. VAT)
— Mn
IPCs Paid (excl. VAT)
214.46 Mn
Total Paid (excl. VAT)
253.06 Mn
Total Paid (incl. VAT)
— Mn
Advance Pend (incl. VAT)
— Mn
IPCs Pend (incl. VAT)
253.06 Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
10.1%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
68.5%
Planned Financial Progress
Planned share of contract value
Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)
Filter financial register
92 matching projects1 active
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 81 | RDA/DRP/NWP/CHI/CHI/08 | Rehabilitation / Improvement of Baththuluoya - Udappuwa - Andimunai Road (B614) … | ST MARY Construction | 83,944,711.21 | — | — | — | — | 15,224,674.76 | 17,965,116.22 | — | — | 15,224,674.76 | — | 17.97Mn Watch21.4% | 17.97Mn 21.4% |
| 82 | RDA/DPR/NCP/ANU/ANU/01 | Rehabilitation / Improvement of Andarawewa - Balaluwewa Road (B501) (21+330 - 21… | Ranuja Construction | 99,497,834.48 | — | — | — | — | — | — | — | — | — | — | — | — |
| 83 | RDA/DRP/NCP/POL/HAB/04 | Rehabilitation / Improvement of washed out section between 30/1 & 30/2 Bridges o… | Lahiru Construction and Consultants (Pvt… | 49,203,550.22 | — | — | — | — | — | — | — | — | — | — | — | — |
| 84 | RDA/DRP/NCP/ANU/MAR/06 | Rehabilitation / Improvement and Retaining wall Construction of bridge No. 3/1 &… | W.M.B. Contractors & Transporter | 112,693,093.11 | 28,343,103.08 | 33,444,861.63 | — | — | 6,175,897.38 | 7,287,558.91 | — | — | 34,519,000.46 | — | 40.73Mn Watch36.1% | 40.73Mn 36.1% |
| 85 | RDA/DRP/NCP/ANU/MED/07 | Rehabilitation / Improvement of Flood Damaged - Shoulder & Embankment Protection… | The Crown Construction | 38,223,285.38 | — | — | — | — | — | — | — | — | — | — | — | — |
| 86 | RDA/DRP/SAB/RAT/PEL/17 | Rehabilitation / Improvement of Balangoda - Bowatta -Kalthota Road (B038) (24+00… | DKS Nishantha Construction | 92,061,086.61 | 16,248,379.38 | 19,173,087.67 | — | — | — | — | — | — | 16,248,379.38 | — | 19.17Mn Watch20.8% | 19.17Mn 20.8% |
| 87 | RDA/DRP/UVA/BAD/BAN/20 | Rehabilitation / Improvement of Bandarawela - Liyangahawela - Poonagala Road (B0… | D K S Construction | 283,401,035.13 | 51,293,460.90 | 60,526,283.86 | — | — | — | — | — | — | 51,293,460.90 | — | 60.53Mn Watch21.4% | 60.53Mn 21.4% |
| 88 | RDA/DRP/NCP/POL/POL/10 | Rehabilitation / Improvement and Construction of New Drainage At 65-78km on Mara… | A.D.M Construction | 29,767,050.53 | 4,266,131.96 | 5,034,035.72 | — | — | 6,804,713.26 | 8,029,561.65 | — | — | 11,070,845.22 | — | 13.06Mn On Track43.9% | 13.06Mn 43.9% |
| 89 | RDA/DRP/EAS/AMP/AMP/01 | Rehabilitation / Improvement of Ampara Uhana Mahoya Road (from 2+400 to 2+800) &… | Ediriweera Construction | 27,878,955.02 | 5,042,900.91 | 5,950,623.07 | — | — | — | — | — | — | 5,042,900.91 | — | 5.95Mn Watch21.3% | 5.95Mn 21.3% |
| 90 | RDA/DRP/WP/GAM/GAM/13 | Rehabilitation / Improvement and Culvert Constructions on Aluthgama- Vigoda Road… | Venus Enterprise | 34,489,854.85 | — | — | — | — | — | — | — | — | — | — | — | — |
| Total | 16,799,029,680.14 | 2,276,780,837.16 | 2,686,401,372.89 | — | — | 905,188,809.07 | 1,068,036,979.06 | 52,935,451.96 | 60,777,795.94 | 3,181,969,646.23 | 52,935,451.96 | 3,754.44Mn 22.3% | 3,815.22Mn 22.7% | |||